Cross County Shopping Center South PD Parking Garage
Location:
Year:
Architect:
Engineer:
Contractor:
Erector:
Project Scope
Sq. Footage:
• One (1) precast framed single bank elevator tower
• Exterior half-helix precast concrete ramp at each level
• Pedestrian precast concrete bridge at second level
Levels/Floors:
Structural Precast Elements:
• 260 Precast Double tees
• 151 Precast Spandrels
• 104 Precast Wall Panels
• 79 Precast Girders
• 66 Precast Single Tees
• 62 Precast Columns
• 28 Precast Shearwalls
• 27 Precast Stairs
• 21 Precast Solid Slabs
• 8 Precast Wall Columns
Precast the Top Choice
The Cross County Shopping Center South PD parking structure located in Yonkers, NY, was a erected in a mere 72 days. This four level, 211,086 sq.ft. precast concrete parking structure holds 709 vehicles.
Speed, Durability and Low-Maintenance Precast
Blakeslee Prestress, Inc. manufactured, delivered and erected the required 806 precast concrete elements for this structure.
They brought more to the project then just their certificates, they brought the ability to coordinate the project from design, to site delivery and erection with unequalled control over each phase of the build. Their indoor, environmentally controlled facility not only assures quality control, but also allows for the production of the precast concrete members during the winter months without slowing for northeast weather conditions.
In the building industry, a proven track record of quality like that of Blakeslee Prestress, Inc. is increasingly important especially in this age of cut backs and skimping. In today’s hard economic times when both time and quality are critical, precast concrete delivers unsurpassed excellence, dependably and when necessary its delivered at record speeds.
Timeline:
• Contract Awarded — September 16, 2008
• Start Precast Erection — April 6, 2009
• Precast Erection Completed — July 10, 2009
• Completion & Occupancy — September 2009