Staples Parking Garage

Location:

Framingham, MA
 

Year:

2011
 

Owner:

Staples, Inc., Framingham, MA
 

Architect:

Gensler, Boston, MA
 

Engineer:

McNamara • Salvia, Boston, MA
 

Contractor:

Creenshaw Construction, lower Falls, MA
 

Erector:

Blakeslee Prestress, Inc., Branford, CT
 

Project Scope

Sq. Footage:

193,792 sf of supported structured area (approx.)
 

Levels/Floors:

3 Levels, 827 spaces (approx.)
 

Structural Precast Elements:

484 Total
• 252 Double Tees
• 15 Girders
• 26 Columns
• 18 Shear Walls
• 40 Lite Walls
• 61 Spandrels
• 9 Stairs
• 23 Solid Slabs
• 40 Wall Panels
 
 
 
 
 
 
 
Staples Parking Garage
Staples Parking Garage
Staples Parking Garage
Staples Parking Garage
Staples Parking Garage
 
 
 
 
 
 
 
 
 
 
 
 
 

The Staples Parking Garage in Framingham, Massachusetts, was open for occupant in December of the 2011 just in time for holiday shoppers. Gensler in Boston designed the three-level, 827-space garage and Crenshaw Construction out of Newton Lower Falls, Massachusetts, served as the general contractor.

Blakeslee Prestress provided unequalled control over all aspects of the design, manufacturing & erection process. Blakeslee Prestress began the precast erection in September 2011 and completed in November of the same year.

Timeline:
Contract Awarded — April 14, 2011
Start Precast Erection — September 26, 2011
Precast Erection Completed — November 11, 2011
Completion & occupancy — December 9, 2011 (approx.)

 